Plumbing milestone, more wire
Today I closed the barn subfloor, having *finally* finished the DWV plumbing for the central bathing area. Michael and Mischa continued doing conduit and wire work. Later this week we hope to have the local electrician make all the connections. Shown here are M & M gluing up some conduit in the ongoing rain. The order errors were corrected today with an afternoon delivery from Omak, so we're back on track. Tomorrow we start putting up walls and vent plumbing, then supply plumbing, then flush!